SSE renewables output rises 31% in first quarter

SSE plc, the Perth-based electricity infrastructure giant, reiterated the financial outlook provided in its full-year results and published a first-quarter trading statement for its Annual General Meeting on Thursday.

The FTSE 100 firm reported continued acceleration of its networks investment, up 83% year-on-year, and a significant increase in renewables output, up 31% year-on-year “reflecting favourable weather and capacity additions.”

Total renewable output in the quarter rose to 3,264 GWh from 2,499 GWh in the prior year quarter.

SSE reiterated its adjusted earnings per share guidance of between 168p and 193p for 2026-27 and between 225p and 250p for 2029-30.

SSE employs 14,000 people and is the largest London-listed firm run from Scotland, with a stock market value of roughly £30 billion.

“The regulated networks businesses have delivered an 83% increase in investment compared to the first quarter of last year as strategic delivery continues to accelerate,” said SSE.

“A total of £0.9bn was invested in networks with construction progressing on the major ASTI and LOTI projects in Transmission, with Distribution investment also increasing ahead of submission of its ED3 business plan in December.

“Over the first three months, generation output from SSE Renewables was 31% higher year-on-year, reflecting more favourable weather conditions and the continued increase in capacity.

“The financial expectations set out in May 2026 remain unchanged and, as usual, continue to be subject to weather, market conditions and plant availability, with the key winter months still to come.”

On its strategic progress, SSE said: “Clear progress is being made in delivering the five-year, £33bn investment plan, and we are on track to invest a record £5bn this year given recent milestones and notable developments including:

“Construction commenced on the Netherton Hub near Peterhead, which will include a 400kV substation, a 132kV substation, and HVDC converter stations to support the Spittal to Peterhead, Eastern Green Link 3 (EGL3) and Eastern Green Link 5 (EGL5) subsea projects.

“Early preparatory work on the Western Isles HVDC link has begun, ahead of main construction commencing later this year.

“Work is progressing strongly at Dogger Bank B with 30 turbines installed with the run-rate of installation significantly exceeding that achieved on the first phase. Commissioning work continues on Dogger Bank A in line with expectations.

“Construction commenced on Platin power station in Ireland, an 180MW Open Cycle Gas Turbine which will be capable of running on natural gas or sustainable biofuels. The plant is due to become operational in 2028 and is backed by 10-year Capacity Market agreements.

“NESO’s Beyond 2030 Update Report identified over £12bn of additional potential investment for SSEN Transmission, taking new identified Future Uncertainty Mechanism spend to more than £17bn, subject to regulatory and planning approvals. This reinforces the significant long-term growth opportunity across the transmission business.

“Ofgem published its Sector Specific Methodology Decision (SSMD) for the RIIO-ED3 regulatory period, which highlighted the need for substantial electrification and investment over the period.

“Coire Glas was included in Ofgem’s LDES ‘minded-to’ list for cap and floor investment support. We will now engage fully with Ofgem to work through a significant number of points of detail which will need to be resolved for the project to progress, in line with our continued focus on capital discipline and with strict adherence to our return thresholds.

“Significant progress has been made on diversifying sources of funding. During the quarter we raised £1.1bn of hybrid debt at an average cost of 4.6% and average tenor of 6.6 years and £1.3bn of new senior debt with an average cost of 5.1% and average tenor of 8.7 years.’

SSS Chief Financial Officer said Barry O’Regan said: “Since announcing our £33bn investment programme to unlock the enormous growth opportunity of UK electricity networks, we are continuing to see real progress as we work to deliver the plan, and in doing so we are underpinning compounding, long-term earnings growth and creating significant value for investors.

“Recent momentum has given increased visibility over the delivery of our 2030s pipeline as the system operator’s strategic plans begin to crystalise and further transmission projects emerge.

“We remain confident in sustained momentum behind a homegrown energy system that will deliver secure, more affordable electricity, support economic growth and create significant long-term investment opportunities across our businesses.”